Phase 1: November 2019 - January 2020
Phase 2: October 2021 - March 2022
The Victoria Drive Relocation Project included the installation of multiple 3152 manholes, 18-way duct bank as well as a 4,162 manhole in the middle of Victoria Drive and Broadway.
Challenge
Congested utility corridor, old growth trees with massive roots required hydrovac and tight time constraints to get manhole installed, which required closing major intersection rerouting buses and traffic. Excavation required onsite engineering due to depth which exceeded 5 metres.
Solution
Comprehensive preplanning along with site meetings with various stake holders
End Result
Installation was completed on time with minimal disruption to public.